- 1 School of Design and Construction, Washington State University, Carpenter Hall, Pullman, WA 99164-2220, United States.
- 2 Department of Civil Engineering, Faculty of Civil and Earth Resources Engineering, Central Tehran Branch, Islamic Azad University, Tehran 1469669191, Iran.
Abstract
High expectations from employers and complex communication between stakeholders in the construction industry, resulted in fundamental changes during the design and construction process. Excellence in communication and coordination is required between stakeholders and automated interdisciplinary change management to meet needs and expectations in the construction industry. Building Information Modeling (BIM) offers numerous benefits, including reducing construction time, cost, and risk while improving project quality, communication, and coordination. However, there are still significant barriers to BIM implementation. Since Iran is in the early stages of BIM implementation, a roadmap for adopting BIM in Iran's construction industry is designed for the first time to exploit BIM benefits in this paper. Face-to-face interviews were conducted with professionals to structure the roadmap. In addition, online interviews were carried out with 16 experts. Furthermore, a Delphi-based approach was employed to reach consensus. The roadmap consists of six main pillars with 53 activities designed to create a matured BIM plan based on local culture and needs. And the roadmap begins with assigning a strong leadership to lead the process. The industry is expected to be motivated to adopt BIM as it learns the benefits associated with BIM. Then, it continues with developing related best practices, rules and regulations. In the third stage, the roadmap encourages the industry to provide the required education and training. In the next pillar, the roadmap follows the establishment and development by defining a contractual platform. In the fifth pillar, the quality of BIM and its results will be measured and compared with expectations and pre-defined goals. Eventually, the government will provide a continuous BIM implementation. The study is expected to facilitate BIM implementation in the Iran construction industry which will improve the quality of Project Management Body of Knowledge (PMBOK) practices. It will help to culminate tangible and intangible project deliverable by reducing time, cost, risks and improving overall quality. Therefore, all stakeholders satisfy the final outcome beside resolving conflicts and interferences.
Keywords
1. Introduction
Numerous studies indicate the advantages of BIM implementation in the construction industry for the whole life cycle of a building, including planning, designing and engineering, construction, and facility management[1-10]. In the early engineering stage, BIM can improve programming by providing a preliminary cost and time estimation, informing the feasibility, reducing possible issues, and documenting the early-stage situation[1-7]. Employing BIM will accelerate and facilitate designing, redesigning,
In Iran, the government strives to minimize the related cost and enhance the opportunity for more construction projects inception with a limited budget allocated to the construction sector. According to the law approved in 2018, only 4% of the total government's budget had been allocated to the construction sector. In 2020, this share has surprisingly decreased to 3.5% of the total budget, while it increased by 5%. Again, in 2021, the government assigned 4% of the total budget to the construction sector[11-13]. There is a significant need to use BIM to produce the best results with the limited budget.
In the engineering phase, BIM enables a Life Cycle Cost Analysis (LCCA)[14,15]. Also, BIM provides a robust feasibility study and conceptual design. Resource conflicts could be realized, and project teams detect clashes before project initiation and make predictive decisions to avoid rework. In the meantime, energy consumption could be optimized using BIM[15]. Time and knowledge are effectively managed, and project understanding is enhanced[16]. Then, the project will be planned effectively, resource management will be enhanced, fabrication will be safe and fast, and the site will be planned efficiently[15]. Also, conflicts between workforces will be reduced through workspace optimization[17]. In addition, BIM aims to reduce material waste[18]. Communication between stakeholders helps to improve physical resource management. BIM helps produce as-built drawing. Furthermore, HSE issues will be controlled. Within the maintenance, facilities, and assets will be managed efficiently. The operation team can anticipate building components' life cycle to inform the operation's warehouse to replace broken elements. The crisis could be managed with fewer injuries and damages[19].
A study showed the positive effect of BIM on project management knowledge areas (PMKAs), in which BIM can improve various aspects of project management, including risk, communication, cost, and schedule[20]. Another study also demonstrated an impressive enhancement in PMKAs and the quality of project management by contributing BIM to the project management activities and deliverables[21]. Iran's construction industry has several significant barriers that hinder companies from applying BIM in their projects. These barriers include a lack of BIM experts, limited awareness around BIM applications, absence of required rules and regulations, inadequate knowledge about BIM usage, lack of support from decision-makers, and high initial cost of providing related software and hardware. Additionally, the rate of investment return is ambiguous to the industry, making it uncertain to use BIM[22]. A BIM implementation roadmap has been proposed for the first time for Iran's construction industry in this paper to address these impediments. The BIM implementation roadmap is based on the current local culture and is designed to satisfy the current needs of the Iranian construction industry. A Delphi-based approach was used to collect experts' opinions through a questionnaire, resulting in a comprehensive roadmap based on six pillars, including 50 tasks within a 5-year anticipated implementation period. The roadmap is expected to guide industry players to actively participate in the process to achieve the pre-defined goals promptly. BIM implementation and continuous improvement are also expected to reach the highest positive potential of BIM in the industry.
2. Literature Review
This paper discusses, on the one hand, advancements in BIM implementation road mapping. On the other hand, it provides a useful roadmap to adopt BIM in Iran's construction industry. For this purpose, the countries that have an approved or proposed roadmap are discussed in the following with a summary of BIM implementation roadmap pillars in Table 1.
Country | Pillars | Ref | |||||||||
Finland | Standards and guidelines for the whole life-cycle | Comprehensive information management know-how | Collaborative model-based processes | Services created through open data | Enabling technology | [25] | |||||
Canada | Engage | Develop | Education | Deploy | Evaluate | Sustain | [28] | ||||
Singapore | Drive BIM collaboration throughout Virtual Design and construction | BIM for Design for Manufacturing & Assembly | New Training programmes at all levels | BIM for Facility Management & Smart City | Research & Development | [31] | |||||
Britain | Approach | Governance | Commons | Enablers | Change | [36] | |||||
Hong Kong | Collaboration | Incentive and Proven Benefits | Standard and Common Practice | Legal and Insurance | Information Sharing and Handover | Promotion and Education | Sufficient Digital Capability and Vendor Support | Risk Management | Global Competitiveness | [41] | |
Mongolia | Developing the Program | Preparation | The Implementation of the Program | [42] | |||||||
Germany | Preparatory Phase | Extended Pilot Phase (Level 1) | BIM Performance Level 1 for New Projects | [43] | |||||||
Portugal | Removing Impediments | Building BIM Capability and Capacity | Incentivizing BIM Adaptors | [27] | |||||||
Malaysia | Standard and Accreditation | Collaboration and Incentives | Education and Awareness | National BIM Library | BIM Guideline and Legal Issues | Special Interest Group | Research and Development | [44] | |||
Ireland | Leadership | Standards | Education &Training | Procurement | [45] | ||||||
Saudi Arabia | Develop BIM Task Group | Set Foundation for BIM Adoption and Implementation | Cultural Change | Education | Investment by Government and Construction Companies | Implementation of BIM | Performance Measurement | Identify and Address Challenges | Review of National Strategy | [46] | |
Brazil | Governance | Infrastructure Technology and Innovation | Legal Framework | Technical Regulation | Investments | Capacity | Induction by the Federal Government | Communication | [47] | ||
Pakistan | Private and Government Based Organizations | Policies Making | [48] | ||||||||
Cooperation with International Organization | Guidelines and Regulations for BIM Implementation | ||||||||||
Awareness Toward Sustainability via BIM | Solutions for Environmental and Energy Crises | ||||||||||
Impact of BIM on XL And L Scale Projects | Impact of BIM on XL, L, M, S Scale Projects | ||||||||||
Nepal | Establishment of Task Group and Develop Policy Documents | Engagement with Stakeholders | Development of Roadmap | Education and Training | Development of Pilot Projects/ Case Studies | Investment in Software and Hardware Infrastructure | Development of Collaborative Working Culture and Assurance of Long-Term | [49] | |||
Ethiopia | Collaboration | Incentive and Proven Benefits | Standards and Common Practices | Legal and Insurance | Information Sharing and Handover | Promotion and Education | Sufficient Digital Capability and Vendor Support | Risk Management | Regional Competitiveness | [50] | |
Algeria | Technology | Policy 1 | Process | Policy 2 | [51] | ||||||
Costa Rica | Technology | Politics | Process | [52] | |||||||
Egypt | Government Engagement | Prepare BIM Guidelines | Training & Education | Collaborative Worldwide Projects | Measurement & Evaluation | Adaption & Promotion | [53] |
BIM: Building information modelling.
In the 1970s, Finland introduced a new approach to digitizing construction[23], and in 2001 started pilot projects[24]. In 2007, BIM became mandated in construction projects[24]. The 5-pillar Finish BIM implementation roadmap relies on five pillars approved in 2014[25], which resulted in 99% of BIM adoption in 2016[26].
The Canadian BIM Council was established in 2008 and required BIM to be used in public sector projects[27]. In 2014, BuildingSMART published the Canadian BIM implementation roadmap with six main pillars[28], which concluded a 67% expansion in the use of BIM in the industry in 2018[29].
Singapore accepted the BIM adoption roadmap before requiring BIM in projects. In this regard, two different versions of the roadmap were published in 2010[30] and 2014[31]. Efforts engendered in 65% BIM implementation in 2014[32]. BIM is currently required in projects with a value of more than 50 million US dollars[33].
In 2017, France approved the BIM implementation roadmap and, at the same time, made BIM mandatory as of this year[34]. In 2015, the BIM usage percentage touched 71%, which revealed a 32% improvement within two years[35].
In the 2000s, South Korea was interested in BIM applications in the construction industry[27]. In 2016, the Ministry of Land, Infrastructure, and Transport (MOLIT) published the Korea BIM implementation roadmap. Since 2016, BIM has been mandated in all public and construction projects valued at more than 50 million US Dollars required by the Public Procurement Service[24].
Spain approved the BIM implementation roadmap in 2015 and subsequently mandated BIM in all public projects with a value of more than 2 million euros[34].
In 2011, Britain legislated to implement BIM level 2 in all public infrastructure projects cost more than 5 million pounds[19,28,29]. The BIM implementation roadmap published by Cambridge University in 2018 consists of 5 pillars[36].
In 2017, Indonesia's industry was motivated to employ BIM[37], and in 2018, the Indonesian BIM implementation roadmap was approved[38]. As a result, 70% of the Indonesian industry adopted BIM level 1 in 2020[39]. Since 2018, BIM become compulsory in all public projects with more than two stories and more than 2000 square meters[40].
Apart from approved roadmaps in pioneer countries, researchers proposed roadmaps in other countries that have not yet been approved. In Table 1, the approved and proposed roadmaps are presented.
Some similar tasks could be identified when considering roadmaps' tasks shown in Table 1. Conceptually, similar tasks are as follows:
• Motivating the industry to join the program could be establishing a leader, a task group, or a government. The task aims to put a robust leader in overall activities to implement policies and keep the process on track.
• Another critical task is to adopt the necessary laws and regulations to prevent deviations from the goals. The other expectation is to create continuous communication with the international community to maintain best practices. The importance is to clarify the requirement over a dynamic platform that will experience change based on international and national developments.
• Since one of the significant obstacles to BIM implementation is the lack of knowledge and awareness[22], it is vital to offer education courses in universities or training courses in non-academic institutes.
• It is also crucial to measure whether the quality of BIM implementation meets the pre-defined goals or the approved standards. Therefore, assessment tools are required to validate the implementation and detect any variations.
•Eventually, stakeholders should ensure that BIM will be used continuously in all construction projects. The roadmap and its steps provide a reliable platform to implement BIM sustainably.
On the other hand, various tasks are included in the roadmaps based on the local needs to compensate for shortages and remove obstacles in each country. Therefore, the Iran BIM implementation roadmap needs a deep understanding of local problem recognition and gathering information specifically for Iran. Thus, the authors conducted a comprehensive literature review below.
Iran is still in the infancy of BIM implementation[54]; meanwhile, Iranian companies are not interested in and generally have limited knowledge about BIM[55]. Only 28% of companies express BIM usage in their projects[56]. Several investigations explored BIM adoption impediments in the Iran construction industry, such as limited knowledge and absence of trained personnel, strict rules, economic issues such as incentives, and software and hardware preparation costs. On the other hand, only 2D drawings are acceptable legally; meanwhile, engineering lead time is more than the traditional method[21,56,57].
Despite research indicating that BIM could accelerate activities in Oil, Gas, and Petrochemical (OGP) projects, its usage is still rare in Iran[58]. According to a survey, 44.2% of Iranian consultants strongly believe in the positive effects of BIM on safety. In addition, through a survey, 33.3% of contractors and 30.2% of clients announced that BIM reduces HSE risks at construction sites[59]. Fakhimi et al. claimed that 54% of non-building construction projects use BIM to enhance project understanding through a 3D model[60]. Furthermore, 48% of non-building construction projects utilize BIM for design purposes, while 20% use it for clash detection. Additionally, 20% apply BIM for planning, 33% to explore quantity, and 34% to assess constructability. Marefat et al. found that Iranian consultants have more knowledge than contractors and clients, attributed to a lack of commitment and interest in BIM among client bodies[59]. Zakeri et al. revealed that despite the allocated budget for the construction industry in Iran, 51% of working hours and 24-46% of productivity are lost at construction sites. Implementing remote construction techniques enables firms to achieve the highest level of efficiency[61].
Fazeli et al.[62] developed an effective model that links cost estimation items to quantities based on the Cost Estimation Standard of Iran in a case study. The developed model provides an acceptable level of accuracy and accelerates the cost estimation while significantly reducing the required resources[62]. Ashtab and Farzad conducted a study to explore the use of BIM in providing tender cost estimation based on the Iran National Bill of Quantities. They claimed that BIM is a feasible and reliable tool for this purpose[63]. Hadavi and Tavakolan developed a model that links project changes to project cost estimation, demonstrating a dedicated platform for decision-making[64]. A study conducted in 2021 proposed a BIM implementation roadmap for petrochemical building projects, focusing on three crucial challenges: process, people, and tools[65]. A platform is also represented by relying on the personnel's required capabilities and the possible strategies to prepare the organization to assist top managers and professionals in facilitating organizational BIM implementation[66]. Rohani and Banihashemi investigated the steps necessary for a successful BIM implementation and concluded that a comprehensive and sequential series of activities is essential. The initial step in achieving a successful BIM implementation is introducing BIM as a newly emerging technological innovation and raising awareness about its potential benefits. Subsequently, it is crucial to establish required standards and regulations about BIM, including developing a standardized contract form specific to BIM projects. These actions help create a solid foundation for effective BIM implementation throughout the industry. Organizations are expected to be attracted to BIM at this stage. In the final step, known as the inter-organizational stage, organizations should strive to overcome and eliminate obstacles that hinder the implementation of BIM[67].
Although BIM is an academic course in ‘construction and engineering management' in Iran the course material is outdated, representing knowledge from ten years ago[54]. Several studies have identified obstacles to BIM implementation in Iran's construction industry, intending to motivate the government to remove these barriers. However, despite these efforts, BIM is still in its preliminary stages, and there is no clear indication of a serious commitment to expanding its use in the industry. While BIM offers many benefits to project stakeholders, its implementation in Iran has experienced very little progress[54]. Not only in Iranian public projects but also in Iranian private projects, BIM implementation encounters many challenges; as Athari Nikooravan and Golabchi concluded, barriers include lack of support from decision-makers, teams showing resistance to change methods, experts reluctant to share data, inefficient workflow to produce and circulate information, lack of a standard contractual framework, absence of a dispute resolution mechanism, interoperable software which faces technical limitations, lack of parametric objects library, and time and expenditure for model development[68]. Toward a widespread BIM adoption in the Iranian industry, Taheripour et al. performed research to identify the barriers and suggest some strategies to resolve them[69]. The authors stated that allocating incentives, involving risk-takers, automating organization structure, and creating a collaborative atmosphere through sufficient and efficient training would improve BIM adoption in the industry.
Studies have shown a lack of contract templates that provide an efficient platform for BIM implementation[70]. In this regard, Mahdian et al. proposed a contract template that aims to resolve BIM barriers based on a case study on Design-Build (DB) and Design-Bid-Build (DBB) projects in Iran[71]. Research conducted in 2020 showed that barriers to BIM adoption in Iran's construction industry are the lack of time to implement BIM, the costs of purchasing software, and the lack of knowledge about the benefits of BIM[57].
This research aims to produce an implementation roadmap based on the current needs and environment of the local construction industry to overcome obstacles.
3. Research Methodology
3.1 Research preparation
A comprehensive literature review is employed to identify local needs and barriers and then to review previous studies with BIM implementation roadmaps. Among all reviewed roadmaps, Canada's[28] and Ireland's[45] BIM implementation Roadmap revealed a close relation to the current environment, considering explored local needs.
The barriers to BIM implementation include: BIM professionals are rare, awareness is insufficient among stakeholders, rules, and regulations are not approved yet, knowledge about BIM is lacking, decision-makers are not demanding, and initial funding to prepare software and hardware is high. In addition, the return of investment (ROI) is ambiguous, making it risky to use BIM. Based on the conducted literature review and the insights obtained from the other countries' roadmaps, the Iran BIM Implementation Roadmap has been drafted. This roadmap highlights the strategies and approaches for resolving the obstacles encountered during BIM implementation.
The drafted roadmap has been discussed through face-to-face interviews with high-level managers. Gathered comments resulted in principal changes in the body of the roadmap. As a result, some tasks have been added to, changed, or removed from the roadmap. Since the interviewees had a substantial experience with an influential role in the industry, and was expected to provide practical and reliable information, which reflected the reality of the construction environment.
3.2 Data collection
The key to success in this research is to gather professional information through a reliable platform. The gathered data will facilitate BIM implementation roadmap requirements determination and aim to prepare a comprehensive judgment. The Delphi-based approach accumulates professionals' perceptions to measure consensus and generate a reliable outcome.
Various types of research relied on the Delphi-based method, resulting in accurate outcomes as shown in Table 2.
Row | Year | Title | Ref. |
1 | 2023 | Building Information Modelling, Integrated Project Delivery, and Lean Construction Maturity Attributes: A Delphi Study | [72] |
2 | 2023 | Justifying the Effective Use of Building Information Modelling (BIM) with Business Intelligence | [73] |
3 | 2023 | Liability Factors and Conceptual Framework for Contracts to Manage Design for Digital Fabrication in Construction Projects | [74] |
4 | 2023 | Verification and validation of a framework for collaborative BIM implementation, measurement and management (CIMM) | [75] |
5 | 2022 | A theoretical BIM-based framework for quantity take-off to facilitate progress payments: the case of high-rise building projects in Vietnam | [76] |
6 | 2021 | A relational framework for smart information delivery manual (IDM) specifications | [77] |
7 | 2021 | Building Operation and Maintenance: A Framework for Simplified Building Information Modeling (BIM) Digital Mobile Application | [78] |
8 | 2021 | Building information modeling based building sustainability assessment framework for Kazakhstan | [79] |
In the Delphi approach, applied analyses are utilized due to their ability to employ theories, regulations, fundamentals, and techniques developed through investigations to answer actual issues. Applied research identifies practical needs and boosts living quality[80]. Regarding its essence, this kind of investigation descriptively and realistically explains real-world situations and facilitate information gathering about the current state toward ease of making decisions[81]. Eventually, considering the nature of this research, which collects information from the field, this research is categorized as "descriptive, exploratory."
The advantages and disadvantages of adopting BIM were initially studied with a deep and extensive literature review, and the essential obstacles were explored, specifically in Iran.
In the next step, a preliminary roadmap is drafted and discussed with professionals to culminate through in-person interviews with experienced experts. The stage resulted in task modification, a roadmap scheme, and a schedule. This step aims to answer the following questions:
• How can we speed up and energize the construction industry to adopt BIM?
• What is the current state of BIM implementation in the construction industry?
• What are the crucial impediments to adopting BIM?
• How much time roughly does the sector need to apply BIM?
• What are the expected achievements relying on BIM?
The interviews resulted in fundamental changes in the pre-defined tasks of the roadmap. A semi-structured questionnaire was designed, with 53 questions in 6 sections, as represented in the appendix, each indicating a pillar, and distributed between 18 professionals to assess the consensus among experts. The questionnaire was designed in 5-point Likert scale and asked participants to add any comment to improve the questionnaire or clarify the ideas. 16 out of 18 experts participated in the investigation. A plurality of the respondents worked at employer organizations (44%), and a quarter worked as consultants. The contractor has the lowest share (12%), almost half of the consultants. Researchers had next to one-fifth of the respondents with 19%. The contribution of each of the mentioned groups is shown in Figure 1.
Figure 1. Research participants.
Table 3 illustrates the education level of participants. As revealed, most participants (68.75%) were master of science graduates. In contrast, only one of the responders was a Ph.D. graduate, and 25% of participants had a bachelor of science degree.
Education | Frequency | Percent of Frequency |
PhD | 1 | 6.25% |
MSc | 11 | 68.75% |
BSc | 4 | 25% |
Total | 16 | 100% |
According to Figure 2, the research indicates that the most significant proportion of participants (37.5%) had less than five years of work experience. In the following, about one-third of respondents have between 10 and 15 years of experience. A quarter of collaborators have 5 to 10 years of experience in the industry, and only about 6% have 15 or more years of background in the construction industry.
Figure 2. Participants working experience.
4. Data analysis
The proposed road map was verified using a Delphi-based method, in which participants' inputs significantly influence the outcome, but there was no established criterion for selecting the participants and measuring their qualifications[82]. Generally, decision-makers, experts with particular expertise, and individuals with strong backgrounds in judgment were invited to fill out the questionnaire. On the other hand, the specific number of respondents has not been defined. Studies suggested a range of collaboration between ten to more than 2000 participants. If the participants are homogeneous, a consensus can be achieved with 10 to 20 respondents, while 15 to 30 respondents are needed to achieve consensus in the case of heterogeneity[83]. In the Delphi method, the consensus is typically reached when at least 80% agreement is obtained for 7-point criteria and 70% agreement for 5-point criteria[82]. However, other studies have defined consensus as 50% or more of the votes being the same, or at least a 70% agreement in the second or third rounds. In the process, questions can be removed if convergence of the answers is observed, helping to streamline the questionnaire in subsequent rounds. Conversely, increasing the gap between results indicate a deviation from consensus[84]. Consensus is measured using the interquartile range, which should be equal to or less than one[85,86]. Four statistical parameters are decisive in evaluating the Delphi-based results: mode, median, mean, and dispersion indexes (including interquartile range and standard deviation)[87]. In addition to achieving agreement through voting, additional criteria are considered to measure consensus. These criteria include ensuring that the standard deviation is equal to or less than 1.64 and the mean is equal to or above 3.25. These criteria serve as additional quantitative measures to evaluate the level of agreement among participants in the Delphi-based method, thereby enhancing the assessment process[77]. Before distributing the questionnaires among anonymous experts, the questionnaire was discussed with three highly qualified professionals and modified to ensure alignment with the subject matter and avoid deviations. The expert opinion-gathering process is presented in Figure 3.
Figure 3. Validation through Delphi approach. SD: standard deviation.
5. Results
5.1 Survey outcome
The process presented in Figure 3 was iterated for three rounds. In the first round, the opinions received were analyzed using key indicators such as percentage of agreement, standard deviation (SD), and mean. Based on the comments received, certain modifications were made to the roadmap tasks, resulting in changes to the questionnaire. The process was repeated for two additional rounds to attain an agreement of over 80% for the specified outlined in the proposed roadmap. By the third round, a consensus was reached on each question using a 5-point Likert scale. The survey outcome is represented in Table 4.
Question | Round 1 | Round 2 | Round 3 | |||||||||
SD | Mean | Consented | Consensus | SD | Mean | Consented | Consensus | SD | Mean | Consented | Consensus | |
Q1 | 1.46 | 3.50 | Yes | 63.75% | 1.49 | 3.73 | Yes | 75.00% | 0.79 | 4.31 | Yes | 86.25% |
Q2 | 1.33 | 3.81 | Yes | 71.25% | 1.33 | 3.81 | Yes | 76.25% | 0.91 | 4.19 | Yes | 83.75% |
Q3 | 1.02 | 4.13 | Yes | 82.50% | 1.02 | 4.13 | Yes | 82.50% | 0.83 | 4.19 | Yes | 83.75% |
Q4 | 1.41 | 3.50 | Yes | 70.00% | 1.31 | 3.88 | Yes | 77.50% | 0.89 | 4.13 | Yes | 82.50% |
Q5 | 1.29 | 3.75 | Yes | 75.00% | 1.12 | 4.06 | Yes | 81.25% | 0.81 | 4.13 | Yes | 82.50% |
Q6 | 1.03 | 4.00 | Yes | 80.00% | 0.93 | 4.06 | Yes | 81.25% | 0.81 | 4.38 | Yes | 87.50% |
Q7 | 0.79 | 4.31 | Yes | 86.25% | 0.79 | 4.31 | Yes | 86.25% | 0.60 | 4.31 | Yes | 86.25% |
Q8 | 0.60 | 4.31 | Yes | 86.25% | 0.60 | 4.31 | Yes | 86.25% | 0.79 | 4.31 | Yes | 86.25% |
Q9 | 1.26 | 3.56 | Yes | 71.25% | 1.26 | 4.00 | Yes | 80.00% | 0.68 | 4.25 | Yes | 85.00% |
Q10 | 1.02 | 4.13 | Yes | 82.50% | 1.02 | 4.13 | Yes | 82.50% | 0.62 | 4.38 | Yes | 87.50% |
Q11 | 0.62 | 4.38 | Yes | 87.50% | 0.62 | 4.38 | Yes | 87.50% | 0.50 | 4.38 | Yes | 87.50% |
Q12 | 1.05 | 3.81 | Yes | 76.25% | 1.09 | 3.88 | Yes | 77.50% | 0.82 | 4.00 | Yes | 80.00% |
Q13 | 1.15 | 3.88 | Yes | 77.50% | 1.15 | 4.00 | Yes | 80.00% | 1.00 | 4.06 | Yes | 81.25% |
Q14 | 1.06 | 4.06 | Yes | 81.25% | 1.31 | 3.63 | No | 81.25% | 0.89 | 4.13 | Yes | 82.50% |
Q15 | 1.33 | 3.81 | Yes | 71.25% | 1.33 | 3.81 | Yes | 71.25% | 0.93 | 4.06 | Yes | 81.25% |
Q16 | 1.33 | 3.81 | Yes | 71.25% | 1.33 | 3.81 | Yes | 71.25% | 0.93 | 4.06 | Yes | 81.25% |
Q17 | 1.33 | 3.81 | Yes | 71.25% | 1.33 | 3.81 | Yes | 71.25% | 0.93 | 4.06 | Yes | 81.25% |
Q18 | 1.45 | 3.69 | Yes | 73.75% | 1.42 | 3.81 | Yes | 72.50% | 1.20 | 4.13 | Yes | 81.25% |
Q19 | 0.50 | 4.38 | Yes | 82.50% | 0.50 | 4.38 | Yes | 82.50% | 0.50 | 4.38 | Yes | 87.50% |
Q20 | 0.68 | 4.25 | Yes | 85.00% | 0.70 | 4.31 | Yes | 76.25% | 0.89 | 4.00 | Yes | 80.00% |
Q21 | 1.17 | 3.81 | Yes | 87.50% | 1.17 | 3.81 | Yes | 87.50% | 0.96 | 4.13 | Yes | 82.50% |
Q22 | 1.15 | 3.56 | Yes | 71.25% | 1.24 | 3.75 | Yes | 86.25% | 0.70 | 4.31 | Yes | 86.25% |
Q23 | 1.20 | 3.63 | Yes | 72.50% | 1.24 | 3.75 | Yes | 76.25% | 0.77 | 4.06 | Yes | 81.25% |
Q24 | 1.18 | 4.06 | Yes | 75.00% | 1.18 | 4.06 | Yes | 75.00% | 0.85 | 4.06 | Yes | 81.25% |
Q25 | 1.17 | 3.81 | Yes | 75.00% | 1.17 | 3.81 | Yes | 75.00% | 0.72 | 4.13 | Yes | 82.50% |
Q26 | 1.11 | 3.81 | Yes | 81.25% | 1.11 | 3.81 | Yes | 81.25% | 0.63 | 4.44 | Yes | 88.75% |
Q27 | 1.20 | 3.63 | Yes | 72.50% | 1.15 | 3.88 | Yes | 76.25% | 0.77 | 4.06 | Yes | 81.25% |
Q28 | 1.00 | 4.06 | Yes | 81.25% | 1.00 | 4.06 | Yes | 76.25% | 0.62 | 4.13 | Yes | 82.50% |
Q29 | 1.28 | 4.19 | Yes | 83.75% | 1.25 | 4.31 | Yes | 77.50% | 0.66 | 4.19 | Yes | 83.75% |
Q30 | 0.73 | 4.44 | Yes | 88.75% | 0.63 | 4.56 | Yes | 81.25% | 0.60 | 4.31 | Yes | 86.25% |
Q31 | 0.77 | 4.06 | Yes | 86.25% | 0.77 | 4.06 | Yes | 86.25% | 1.25 | 4.31 | Yes | 86.25% |
Q32 | 0.48 | 4.69 | Yes | 91.25% | 0.48 | 4.69 | Yes | 91.25% | 0.63 | 4.56 | Yes | 91.25% |
Q33 | 0.85 | 4.06 | Yes | 81.25% | 0.85 | 4.06 | Yes | 81.25% | 0.77 | 4.06 | Yes | 81.25% |
Q34 | 0.68 | 4.25 | Yes | 93.75% | 0.68 | 4.25 | Yes | 93.75% | 0.62 | 4.63 | Yes | 92.50% |
Q35 | 1.15 | 3.63 | Yes | 72.50% | 0.98 | 3.81 | Yes | 81.25% | 0.85 | 4.06 | Yes | 81.25% |
Q36 | 1.18 | 3.94 | Yes | 85.00% | 1.18 | 3.94 | Yes | 85.00% | 0.68 | 4.25 | Yes | 85.00% |
Q37 | 1.36 | 3.88 | Yes | 76.25% | 1.36 | 3.88 | Yes | 76.25% | 0.68 | 4.06 | Yes | 81.25% |
Q38 | 1.10 | 4.00 | Yes | 80.00% | 1.10 | 4.00 | Yes | 78.75% | 0.68 | 4.25 | Yes | 85.00% |
Q39 | 1.31 | 3.56 | Yes | 71.25% | 1.35 | 3.69 | Yes | 80.00% | 0.75 | 4.19 | Yes | 83.75% |
Q40 | 0.81 | 3.88 | Yes | 77.50% | 0.82 | 4.00 | Yes | 80.00% | 0.82 | 4.00 | Yes | 80.00% |
Q41 | 0.51 | 4.56 | Yes | 91.25% | 0.51 | 4.56 | Yes | 91.25% | 0.51 | 4.56 | Yes | 91.25% |
Q42 | 1.22 | 3.81 | Yes | 76.25% | 1.24 | 3.94 | Yes | 78.75% | 0.83 | 4.19 | Yes | 83.75% |
Q43 | 0.89 | 3.88 | Yes | 77.50% | 0.73 | 4.00 | Yes | 80.00% | 0.73 | 4.00 | Yes | 80.00% |
Q44 | 0.52 | 4.50 | Yes | 90.00% | 0.52 | 4.50 | Yes | 90.00% | 0.52 | 4.50 | Yes | 90.00% |
Q45 | 0.75 | 4.19 | Yes | 83.75% | 0.75 | 4.19 | Yes | 83.75% | 0.75 | 4.19 | Yes | 83.75% |
Q46 | 0.77 | 4.25 | Yes | 85.00% | 0.50 | 4.38 | Yes | 87.50% | 0.50 | 4.38 | Yes | 87.50% |
Q47 | 1.00 | 3.94 | Yes | 78.75% | 0.85 | 4.06 | Yes | 81.25% | 0.85 | 4.06 | Yes | 81.25% |
Q48 | 0.68 | 4.25 | Yes | 85.00% | 0.60 | 4.31 | Yes | 86.25% | 0.60 | 4.31 | Yes | 86.25% |
Q49 | 0.48 | 4.69 | Yes | 93.75% | 0.48 | 4.69 | Yes | 93.75% | 0.48 | 4.69 | Yes | 93.75% |
Q50 | 0.51 | 4.44 | Yes | 88.75% | 0.51 | 4.44 | Yes | 88.75% | 0.51 | 4.44 | Yes | 88.75% |
Q51 | 1.32 | 4.00 | Yes | 80.00% | 1.34 | 4.06 | Yes | 81.25% | 0.89 | 4.38 | Yes | 87.50% |
Q52 | 0.72 | 4.38 | Yes | 87.50% | 0.73 | 4.44 | Yes | 88.75% | 0.73 | 4.44 | Yes | 88.75% |
Q53 | 0.48 | 4.69 | Yes | 93.75% | 0.48 | 4.69 | Yes | 93.75% | 0.48 | 4.69 | Yes | 93.75% |
SD: standard deviation.
5.2 Proposed road map
Next, the six pillars of the proposed road map will be discussed. Three colors have separated each party's responsibilities: blue indicates government duties, yellow represents academia, and green shows industry such as contractors, consultants, subcontractors, manufacturers, and vendors. Five years have been anticipated to implement the roadmap perfectly, while it requires monitoring the progression regularly.
5.2.1 Leadership
As illustrated in Figure 4, this pillar is compelling government bodies, industry, and academia toward an effective movement to implement BIM in the building industry under a robust leader, emitted between highly qualified and experienced managers. The leadership should have a clear vision of defining long-term goals and expectations. Leadership should align all BIM implementation participants and unite them toward the goal. Incentives will energize firms to adopt BIM and accelerate the movement creation. Therefore, required budget or policies could be allocated, such as a tax exemption or extra tender technical evaluation. One of the main concerns is the persistence of using conventional methods. Therefore, the leadership must encourage the parties to accept and implement fundamental changes. An effective leader should convince industry and academia to contribute to adopting BIM and establish professional working groups to collaborate with international teams to exchange state-of-the-art experiences and advancements to enhance national movement. Initially, four goals are expected to achieve the robust and effective leadership required to create a comprehensive movement and integrate academia, private and public sectors. The leader should maintain novel and continuously communicate with pioneer and proactive professional groups.
Figure 4. Leadership pillar. BIM: Building information modelling.
5.2.2 Standardization
This process deals with the legislation of legal and technical rules and regulations, recommendations, and other related materials. The legal and technical package should intellectually align with Iran's construction industry needs. The process should facilitate pursuing, discovering, and employing new international advancements and best practices. In this regard, the National BIM Standard Committee should first be formed to recommend and prepare legal and technical material, follow them up for approval or modification and notification, and identify implementations and report deviations in Iran. The committee should define fundamental strategy and national goals. Then, the committee should identify any potential risks and impediments against new processes and procedures. Then, the committee should obtain confirmation of rules, regulations, recommendations, codes, and standards approval. It is also vital for the committee to communicate with active international groups, which helps find new developments. So that all the legal and technical material should be updated continuously. Since some companies employ BIM, a framework is required to evaluate qualification and rank companies during a project team or award selection. It assists employers in analyzing bidders' ability to implement BIM in their projects and could influence the technical qualification result. An online monitoring system is defined to monitor BIM implementation quality with the expected one. The pillar's structure is presented in Figure 5.
Figure 5. Standardization pillar. BIM: Building information modelling.
5.2.3 Education
This pillar points required activities to share knowledge and train individuals and organizations to implement BIM. Before any action, an executive board should be formed. An online assessment platform can identify individual and organizational deficiencies and weaknesses. In addition, the board should provide an education framework to compensate for training requirements. The process should be directed by academia or training professionals, who can identify needs and deliver effective training. Also, a shortlist should be drawn to issue the names of eligible training institutes. In addition, equally for each trainee, the training platform should provide a standard, reliable, and practical level of expertise. The academia is typically in charge of conducting analytical research and finding out what is hindering BIM implementation nationally. The other aspect of education to fulfill the market need to employ recent graduates is to define BIM courses in the university. Therefore, students have an acceptable knowledge of BIM immediately after graduation. A successful education process demands workforce development, moving in parallel with international advancements. So, the board should communicate with international groups to update education contents.
Figure 6 shows the education pillar and subtasks.
Figure 6. Education pillar. BIM: Building information modelling.
5.2.4 Development
The development pillar (Figure 7) follows the framework development of a contractual platform and aims to approve a contract draft that satisfies employers' needs to implement BIM in their projects. Therefore, it is essential to legislate a technical and legal platform, and a standard language of contract should be defined to issue the standard contract draft relying on the framework. Various drafts must be approved to comply with different project delivery methods. The most crucial step that should be taken in this pillar is planning to mandate BIM in projects. As BIM is not expected to be implemented in all projects, it is necessary to consider the circumstances under which BIM is required.
Figure 7. Development pillar . BIM: Building information modelling.
5.2.5 Assessment
This process (Figure 8) aims to establish the criteria to measure the BIM maturity and the level of BIM implementation in construction projects. The pillar follows to attract employers' attention and support the continuous assessment of the current BIM adoption state. Initially, the key performance indexes (KPIs) should be defined and developed continuously. Then, an online dashboard needs to be created to measure maturity level based on KPIs, and the outcomes should be kept in a database. It helps to trace improvement in BIM implementation and measure current and expected achievements to take corrective decisions. The results should be incorporated into contract templates to address any identified deficiencies. Furthermore, amendments can be made to the contract drafts to reflect the recommendations and insights derived from the Delphi-based method. Integrating these results into the contract templates and making necessary modifications ensures that the contract adequately accounts for the identified areas of improvement.
Figure 8. Assessment pillar. BIM: Building information modelling.
5.2.6 Reliability
This pillar guarantees persistent BIM implementation regardless of whether the project is public or private and the size of the project. The pillar aims for BIM adoption development in the construction industry. Also, it persuades rules and regulations to be reviewed due to international advancements. Therefore, the latest revision of laws, regulations, protocols, and industry standards should be applied. On the other hand, by documenting achievements, the whole industry will be motivated to exploit BIM. Meantime, industry and academia should cooperate through BIM implementation. So, a close relationship with international groups is required to use prosperous experiences. Maintaining these experiences will result in BIM implementation improvement ( Figure 9).
Figure 9. Reliability pillar. BIM: Building information modelling.
6. Discussion
This study proposed a roadmap toward BIM implementation in the Iranian construction industry through a comprehensive survey. First, removing the barriers to BIM adoption is necessary to achieve the intended goals. BIM adoption impediments are lack of knowledge, absence of experts, strict rules, economic issues such as incentives, and initial funding to prepare suitable software and hardware. Meanwhile, the accepted drawing format is 2D; the engineering phase also requires more time than the traditional approach due to lack of training and experience. Moreover, decision-makers are busy with resolving daily problems and do not have additional capacity to develop BIM implementation in projects. Also, lack of training causes limited awareness about BIM advantages and its positive effect on the final deliverables. Additionally, it is essential to establish a regulatory system that can approve and implement practical rules specifically tailored to the construction industry environment in Iran. This regulatory framework should aim to address local issues and provide incentives to the industry. So, it can effectively contribute to solving industry-specific challenges and foster growth and development within the construction sector. In the same vein, since Iranian firms face financial issues, they require motivation to solve them; for instance, the employer could allocate incentives or exemptions. Furthermore, for widespread use of BIM, the government should earn industry trust, and it is feasible through performing pilot projects to illustrate how BIM could serve stakeholders and ROI in the short term. Meantime, while the highest turnover happens in the construction phase, the private sector prefers to spend less time in the engineering phase; however, engineering is generally more time-consuming with BIM[21,55-57,59].
The proposed road map has been shaped by the needs and impediments recognition through a comprehensive literature review. Then, the primitive roadmap structure was discussed with professionals, and the roadmap structure was deeply affected. Next, a structured questionnaire has been designed with 53 questions in 6 main sections. The questionnaires were distributed among 16 experts, and their opinions were collected in three rounds. Eventually, the roadmap has been modified based on the results. In the end, a roadmap has been proposed adapted to Iran's needs and impediments. Nevertheless, research experienced difficulties as follows:
• Professionals who contributed to the face-to-face interview to modify the primitive structure are not accessible.
• Highly qualified experts were not interested in cooperating with the research. In the meantime, finding experts with reliable opinions and sufficient knowledge proved a significant challenge.
• To obtain a comprehensive result, the participation of all stakeholders in the research was essential. In industry, employers and contractors particularly had limited knowledge about BIM.
7. Conclusion
Since BIM provides many benefits to the construction industry, a roadmap for implementing BIM for Iran's construction industry is proposed in this research. The roadmap stands on local culture and built environment to fulfill needs. A 6-pillar roadmap, based on comprehensive literature and global achievements, has been prepared, consisting of 53 tasks. This roadmap incorporates insights and best practices from various sources to provide a well-rounded and comprehensive approach. The BIM implementation is expected to contribute to the construction industry through overall improvement of PMBOK and to the society as:
• Provides easy-access information during the life-cycle from inception to decommissioning.
• Assists project managers to control time, cost, and progress in real-time.
• Provides real-time quality control to improve the overall quality of deliverables.
• Reduces risks and aims to make predictive and corrective decisions while measuring their effects.
• Reducing HSE and environmental impacts.
• Reduces time and cost of the project.
• Eliminates clashes, interferences, and reworks.
• Facilitating help during a crisis.
• Implementing circular economy.
For this purpose, initially, a primitive roadmap structure was designed. Then, to measure its reliability and practicability, the draft has been discussed with three professionals with invaluable experience in the industry and enough knowledge about public and private sector issues. Face-to-face interviews resulted in fundamental changes in the roadmap tasks to transform them into realistic and practical activities. Subsequently, the opinions of 16 experts were gathered using a Delphi-based approach. Experts have been selected from industry and academia with different working experiences. Interviews led to modifying some tasks based on current local industry needs. The consensus has been achieved through three rounds of interviews, and the roadmap has been stable. The roadmap provides a progressive sequence from the current infancy estate to a mature expected estate over five years. It is crucial to appoint a powerful and charismatic leader to create a movement in the industry to ensure continuous and persistent BIM adoption. Also, periodic monitoring aims to measure the achievements compared with expectations and detect any deviation to take corrective actions. BIM implementation project participants are expected to experience more satisfaction in tangible and intangible achievements, such as cost and time-saving, quality improvement, and reputation rectification. The roadmap pillars are as follows:
• The first pillar follows to make an efficient movement in the industry by employing a decisive leader who stands out with a realistic view of the current state and perspective on the industry's future needs.
The second pillar pinpoints adapting the rules, regulations, and technical instructions to fill gaps.
• The objective of the third pillar is to address the shortage of experts in the industry by focusing on education and training initiatives. This pillar aims to provide the necessary knowledge and skills to compensate for the lack of expertise. Additionally, it seeks to promote general awareness and understanding of the application of BIM and highlight the benefits associated with its implementation. By doing so, this pillar aims to enhance the overall knowledge and capabilities within the industry.
• It is also expected that through this pillar, BIM courses and disciplines will be created in the university.
• The fourth pillar points out defining a contractual language to employ a uniform contract template that could satisfy employers' needs.
•The fifth pillar provides trustworthy evaluations to correct deviations and compare achievements with expectations.
• The sixth pillar aims to implement BIM continuously and persistently.
Impediments in the way of this research were difficulties in setting appointments with professionals for a face-to-face interview. On the other hand, qualified experts were less interested in participating in the study due to their busy and intensive work schedules. Meanwhile, employers and contractors have a lower knowledge level about BIM than researchers and consultants.
8. Limitation and Future Research
This research is limited to proposing a BIM implementation roadmap for the Iran construction industry. Although the proposed roadmap could provide a potential benefit for other countries, it needs an in-depth investigation to explore each specific or local needs. The future area of research could be worked on developing tasks in detail, such as focusing on one of the most critical pillars, education, proposing a practical procedure based on best practices, or drafting the required rules and regulations based on successful regional or international practices.
Authors contribution
All authors contributed equally to this work.
Conflicts of interest
Javad Majrouhi Sardroud is the Editorial Board member of JBDE, and other authors declare no conflict of interest.
Ethical approval
Not applicable.
Consent to participate
Not applicable.
Consent to publication
Not applicable.
Availability of data and materials
The data and materials during the current study are available from the corresponding author on reasonable request.
Funding
None.
Copyright
© The Author(s) 2023.
References
-
1. Azhar S. Building information modeling (BIM): trends, benefits, risks, and challenges for the AEC industry. Leadership Manage Eng. 2011;11:241-252.
[DOI] -
2. Anumba CJ, Dubler CR, Goodman S, Kasprzak C. BIM project execution planning guide. Computer integrated construction research program, the Pennsylvania State University; 2010. Avaialble from: https://www.researchgate.net/publication. (accessed October 8, 2023)
-
3. Latiffi AA, Mohd S, Kasim N, Fathi MS. Building information modeling (BIM) application in malaysian construction industry. Int J Constr Eng Manage. 2013;2(4A):1-6.
[DOI] -
4. Shou W, Wang J, Wang X, Chong HY. A comparative review of building information modelling implementation in building and infrastructure industries. Arch Comput Methods Eng. 2015;22:291-308.
[DOI] -
5. BorjeGhale RM, Sardroud JM. Approaching industrialization of buildings and integrated construction using building information modeling. Proc Eng. 2016;164:534-541.
[DOI] -
6. Sardroud JM, Mehranpour H, Arzanloo A. An investigation into the integration of building information modeling with pre-construction industry in the developed countries and Iran. In: Creative construction e-conference. 2021 Jun 29-30;
[DOI] -
7. Sardroud JM, BorjeGhaleh RM, Kameli M. An investigation on building information modelling role in industrialization of building. In: Creative construction conference 2016; 2016 Jun 25-28;.Budapest, Hungary. 2016. p. 650-660. Available from: https://2016.creative-construction-conference.com
-
8. Barlish K, Sullivan K. How to measure the benefits of BIM-A case study approach. Autom Constr. 2012;24:149-159.
[DOI] -
9. Bennett L, Mahdjoubi L. Construction health and safety, BIM and cloud technology proper integration can drive benefits for all stakeholders. In: 2013 IEEE International conference on cloud computing technology and science. 2013 Dec 2-5;
[DOI] -
10. Kameli M, Hosseinalipour M, Majrouhi Sardroud, Ahmed SM, Behruyan M. Improving maintenance performance by developing an IFC BIM/RFID based computer system. J Ambient Intell Humanized Comput. 2021;12:3055-3074.
[DOI] -
11. Plan and budget Organization [Internet]. Budget 2019: Building a strong, united Singapore. 2019. Available from: https://www.mof.gov.sg/docs/default-source
-
12. Plan and budget Organization [Internet]. Budget 2020: advancing as one Singapore. 2020.. Available from: https://www.mof.gov.sg/docs/librariesprovider3
-
13. Plan and budget Organization [Internet]. Budget 2021: Emerging stronger together. 2021. Available from: https://www.mof.gov.sg/docs/librariesprovider3
-
14. Lee J, Yang H, Lim J, Hong T, Kim J, Jeong K. BIM-based preliminary estimation method considering the life cycle cost for decision-making in the early design phase. J Asian Archit Build Eng. 2020;19(4):384-399.
[DOI] -
15. Ullah K, Lill I, Witt E. An overview of BIM adoption in the construction industry: benefits and barriers. In: 10th Nordic Conference on Construction Economics and Organization; 2019 May 7-8; Tallinn, Estonia. Leeds: Emerald Publishing Limited; 2019. p. 297-303.
[DOI] -
16. Crowther J, Ajayi SO. Impacts of 4D BIM on construction project performance. Int J Constr Manag. 2019;21(4):724-737.
[DOI] -
17. Tran NNT, Pham HL.. In: Proceedings of the 2020 4th International Conference on E-Education, E-Business and E-Technology; 2020 June 5-7; Shanghai, China. New York: Association for Computing Machinery. 2020;
[DOI] -
18. Heigermoser D, De Soto, Abbott ELS, Chua DKH. BIM-based last planner system tool for improving construction project management. Autom Constr. 2019;104:246-254.
[DOI] -
19. Zahedi F, Majrouhi Sardroud J, Kazemi S. Global BIM implementation roadmaps: an extensive review. In: Skibniewski MJ, Hajdu M, editors. Creative Construction e-Conference 2022. 2022 Jul 9-11; Online. 2022. p. 382-395.
[DOI] -
20. Shaqour EN. The role of implementing BIM applications in enhancing project management knowledge areas in Egypt. Ain Shams Eng J. 2022;13(1):101509-101509.
[DOI] -
21. Fazli A, Fathi S, Enferadi MH, Fazli M, Fathi B. Appraising effectiveness of building information management (BIM) in project management. Proc Technol. 2014;16:1116-1125.
[DOI] -
22. Zahedi F, Sardroud JM, Kazemi S. Global BIM adoption movements and challenges: an extensive literature review. In: Skibniewski MJ, Hajdu M, editors. Creative construction e-conference 2022;2022 July 9-11; Online. 2022. p. 382-395.
[DOI] -
23. Smith P. BIM implementation-global strategies. Procedia Engineering. 2014;85:482-492.
[DOI] -
24. Bolpagni M. The implementation of BIM within the public procurement: A model-based approach for the construction industry. Finland: VTT Technical Research Centre; 2013. Available from: https://publications.vtt.fi/technology
-
25. Savolainen T. buildingSMART [Internet]. Available from: https://www.buildingsmart.org
-
26. European Construction Sector Observatory. Policy measure fact sheet Finland. 2016. Available from: https://single-market-economy.ec.europa.eu
-
27. Silva MJF, Salvado AF, Couto P, E Azevedo. Roadmap proposal for implementing building information modelling (BIM) in Portugal. Open J Civ Engi. 2016;6(3):475-481.
[DOI] -
28. BuildingSMART [Internet]. The roadmap to lifecycle building information modeling in the Canadian AECOO community. 2016. Available from: https://www.cisc-icca.ca/wp-content
-
29. Bhatti IA, Abdullah AH, Nagapan S, Bhatti NB, Sohu S, Jhatial AA. Implementation of building information modeling (BIM) in Pakistan construction industry. Engi. Technol Appl Sci Res;
[DOI] -
30. Building and Construction Authority. Singapore's BIM roadmap. 2011.
-
31. Cheng TF [Internet]. Singapore BIM journey. 2017. Available from: https://www.icom.uni-hannover.de/icom_alt
-
32. Rakib MFH, Howlader S, Rahman M. Factors affecting the BIM adoption in the construction industry of Bangladesh. Southeast Univ J Sci Eng. 2020;14(1):252-259. Available from: https://www.kuet.ac.bd/webportal/ppmv2
-
33. Mustaffa NE, Salleh RM, Tajul Ariffin HLB. Experiences of building information modelling (BIM) adoption in various countries. In: 2017 International conference on research and innovation in information systems (ICRIIS); 2017 Jul 16-17; Langkawi, Malaysia. Piscataway: IEE; 2017. p.1-7.
[DOI] -
34. Panteli C, Polycarpou K, Morsink-Georgalli FZ, Stasiuliene L, Pupeikis D, Jurelionis A, et al. Overview of BIM integration into the construction sector in European Member States and European Union Acquis. IOP Conf Ser: Earth Environ Sci. 2020;410(1):012073-012073.
[DOI] -
35. Gerges M, Austin S, Mayouf M, Ahiakwo O, Jaeger M, Saad A, et al. An investigation into the implementation of building information modeling in the middle east. J Inf Technol Constr. 2017;22(1):1-15. Available from: https://www.itcon.org/papers
-
36. Enzer M, Bolton A, Boulton C, Byles D, Cook A, Dobbs L, et al. Roadmap for delivering the information management framework for the built environment. Apollo-University of Cambridge Repository. 2019;
[DOI] -
37. Telaga AS. A review of BIM (Building Information Modeling) implementation in Indonesia construction industry. IOP Conf Ser Mater Sci Eng. 2018;352(1):012030-012030.
[DOI] -
38. BIM PUPR, IBIMI. Panduan adopsi BIM dalam organisasi [Internet].Jakarta: Pusat Litbang Kebijakan dan Penerapan Teknologi; 2018. Available from: https://ru.scribd.com/document
-
39. Van Roy, Firdaus A. Building information modelling in Indonesia: knowledge, implementation and barriers. J Constr Dev Countries. 2020;25(2):199-217.
[DOI] -
40. Sopaheluwakan MP, Adi TJW. Adoption and implementation of building information modeling (BIM) by the government in the Indonesian construction industry. Mater Sci and Eng. 2020;930(1):012020-012020.
[DOI] -
41. Construction industry council [Internet]. Final Draft Report of the Roadmap for BIM Strategic Implementation in Hong Kong's Construction Industry. Hong Kong: Construction Industry Council; 2013. Available from: https://www.cic.hk/files
-
42. Ismail NAA, Chiozzi M, Drogemuller R. An overview of BIM uptake in Asian developing countries. AIP Conf Proc. 2017;1903(1):080008-080008.
[DOI] -
43. Federal Minister of Transport and Digital Infrastructure [Internet]. Road map for digital design and construction. Berlin: Federal Minister of Transport and Digital Infrastructure; 2015. Available from: https://bmdv.bund.de/SharedDocs
-
44. CIDB [Internet]. Building information modeling roadmap for Malaysia's construction industry, workshop report (Series 2). Malaysia: construction industry development board Malaysia; 2017. Available from: https://smart.cidb.gov.my
-
45. GCCC [Internet]. A public sector BIM adoption strategy. 2017. Available from: https://constructionprocurement.gov.ie
-
46. Alhumayn SA [Internet]. Developing a framework for BIM implementation in the Saudi Arabian construction industry. West Midlands: University of Wolverhampton; 2018. Available from: http://hdl.handle.net/2436/621927
-
47. Comite estrategico do BIM. BIM BR Construção Inteligente. 2017.
-
48. Girginkaya Akdag, Maqsood U. A roadmap for BIM adoption and implementation in developing countries: the Pakistan case. Int J Archit Res. 2020;14(1):112-132.
[DOI] -
49. Marasini R. Strategies for adoption of building information modelling (BIM) in Nepal: lessons learned from the UK and other countries. In: Proceedings of Society of Nepalese Engineers (UK). The Society of Nepalese Engineers; 2018. p.60-67.
[DOI] -
50. Ethiopian Construction Project Management Institute. Roadmap for adoption and implementation of BIM technology in the Ethiopian architectural, engineering and construction (AEC) industry. FDRE Minstry of Urban Development and Construction; 2019. Available from: https://www.scribd.com/document
-
51. Bouguerra K, Yaik-Wah L, Ali KN. A preliminary implementation framework of building information modelling (BIM) in the Algerian AEC industry. Int J Built Environ Sustain. 2020;7(3):59-68.
[DOI] -
52. Zúñiga MC, Abdelnour EM. Proposal for the implementation of BIM methodology in public works projects of Costa Rica. Métodos Mater. 2020;10:35-47. Spanish.
[DOI] -
53. Abdallah MR, Ahmed AZ, Abdalla SS. Towards a strategic roadmap for a successful BIM implementation in the Egyptian community. J Eng Appl Sci. 2020;67:333-352. Available from: https://www.jeasonline.org/paper/1097/preview
-
54. Zare SMHM, Ahangar AK. A comparative study on BIM (Building Information Modeling) implementation and maturity across different countries with a review on Iran. In: 3rd International Conference on Building Information Modelling 2020; 2020 Jun 9-10; Tehran, Iran. Available from: https://bimconf.com/wp-content
-
55. Hosseini MR, Azari E, Tivendale L, Chileshe N. Barriers to adoption of building information modeling (BIM) in Iran: preliminary results. In: The 6th International Conference on Engineering. Project, and Production Management (EPPM2015);Gold Coast:Australia-Australia.
[DOI] -
56. Hosseini MR, Azari E, Tivendale L, Banihashemi S, Chileshe N. Building information modeling (BIM) in Iran: an exploratory study. J Eng Proj Prod Manage. 2016;6(2):78-89.
[DOI] -
57. Nemati B, Zandi S, Aminnejad B, Davarazar M, Sheikhnejad Y, Jahanianfard D, et al. Building information modelling execution in administrative and commercial spaces in Iran-a fuzzy-delphi criteria prioritization. J Settlements Spat Plann. 2020;6:17-27.
[DOI] -
58. Fakhimi A, Sardrood JM, Mazroi A, Ghoreishi SR, Azhar S. Influences of building information modeling (BIM) on oil, gas and petrochemical firms. Sci Technol Built Environ. 2017;23(6):1063-1077.
[DOI] -
59. Marefat A, Toosi H, Mahmoudi Hasankhanlo. A BIM approach for construction safety: applications, barriers and solutions. Eng Constr Archit Manage. 2019;26(3):1855-1877.
[DOI] -
60. Fakhimi A, Rezaee P, Kiani Y, Sardrood JM. Empowering of non-building industry with building information modeling (BIM). In: 1st National Conference on Applied Research in Structural Engineering and Construction Management; 2016; (In Persian). Available from: https://civilica.com/doc/580240
-
61. Zakeri M, Olomolaiye PO, Holt GD, Harris FC. A survey of constraints on Iranian construction operatives' productivity. Constr Manage Econ. 1996;14(5):417-426.
[DOI] -
62. Fazeli A, Dashti MS, Jalaei F, Khanzadi M. An integrated BIM-based approach for cost estimation in construction projects. Eng Constr Archit Manage. 2021;28(9):2828-2854.
[DOI] -
63. Ashtab M, Farzad MR. Aligning tender cost estimation practices in Iran with BIM. Int J Eng Technol. 2018;10(4):329-334.
[DOI] -
64. Hadavi P, Tavakolan M.. In: Construction Research Congress 2018: Construction Information Technology. 2018 Apr 2-4; New Orleans: Louisiana. 2018. p 542-551;
[DOI] -
65. Fakhimi A, Sardroud JM, Mazroi A, Goreishi SR, Azhar S. Building information modeling deployment in oil, gas and petrochemical building information modeling deployment in oil, gas and petrochemical industry: an adoption roadmap. Civ Eng Infrastruct J. 2021;54(2):281-299.
[DOI] -
66. Rajabi MS, Rezaeiashtiani M, Radzi AR, Famili A, Rezaeiashtiani A, Rahma RA. Underlying factors and strategies for organizational BIM capabilities: the case of Iran. Appl Syst Innovation. 2022;5(6):109-109.
[DOI] -
67. Rohani N, Banihashemi SY. Identifying and prioritizing the barriers to BIM implementation in Iran. Amirkabir J Civ Eng. 2022;54(2):157-160.
[DOI] -
68. Athari Nikooravan, Golabchi M. Analysis of barriers of implementing BIM in construction industry: Iranian private projects. Sharif J Civ Engi. 2023;39(2):69-80.
[DOI] -
69. Taheripour S, Azizi M, Eshtehardian E. Solutions to facilitate the acceptance of building information modeling technology in Iranian building companies, based on the effects of national culture dimensions. J Technol Dev Manage. 2022;9(4):129-150.
[DOI] -
70. Nilchian S, Sardroud JM, Darabpour M, Tafreshi ST. The Study of the Contracts of Building Information Model (BIM) and the Approach to its Contractual Framework Codification. AmirKabir J Civ Eng. 2021;53(8):3239-3260.
[DOI] -
71. Mahdian A, Jalal MP, Roushan TY. Contractual risks of BIM implementation and the proposed contract form for DBB and DB projects. J Leg Aff Dispute Resolut Eng Constr. 2023;15(1):06522003-06522003.
[DOI] -
72. Rashidian S, Drogemuller R, Omrani S. Building information modelling, integrated project delivery, and lean construction maturity attributes: a delphi study. Buildings. 2023;13(2):281-281.
[DOI] -
73. Ma X, Li X, Yuan H, Huang Z, Zhang T. Justifying the effective use of building information modelling (BIM) with business intelligence. Buildings. 2023;13(1):87-87.
[DOI] -
74. Ng MS, Hall DM, Hsieh SH. Liability factors and conceptual framework for contracts to manage design for digital fabrication in construction projects. J Leg Aff Dispute Resolut Eng Constr. 2023;15(1):04522043-04522043.
[DOI] -
75. Pidgeon A, Dawood N. Verification and validation of a framework for collaborative BIM implementation, measurement and management (CIMM). Smart Sustainable Built Environ. 2022;12(4):847-871.
[DOI] -
76. Nguyen T-Q, Lou ECW, Nguyen BN. A theoretical BIM-based framework for quantity take-off to facilitate progress payments: the case of high-rise building projects in Vietnam. Int J Build Pathol Adapt. 2024;42(04):704-728.
[DOI] -
77. Jeon K, Lee G, Kang S, Roh H, Jung J, Lee K, et al. A relational framework for smart information delivery manual (IDM) specifications. Adv Eng Inf. 2021;49:101319-101319.
[DOI] -
78. Ali AS, Zakaria N, Zulkifly UKZ. Building operation and maintenance: a framework for simplified building information modeling (BIM) digital mobile application. Int J Interact Mobile Technol. 2021;15(20):146-160.
[DOI] -
79. Akhanova G, Nadeem A, Kim JR, Azhar S, Khalfan M. Building information modelingbased building sustainability assessment framework for Kazakhstan. Buildings. 2021;11(9):384-384.
[DOI] -
80. Hafez Nia MR. Introduction to research methodology in humanities. Tehran: SAMT Publication; 1998.
-
81. Sarmad Z, Bazargan A, Hejazi E. Research methods in behavioral sciences. Agha Publishing House. 2006.
-
82. Hsu C, Sandford BA. The Delphi Technique: Making Sense of Consensus. Pract Assess. Res Eval;
[DOI] -
83. Martino JP. Technological Forecasting for decision making. 3rd ed. New York: McGraw-Hill Inc; 1993.
-
84. Schmidt RC. Managing Delphi surveys using nonparametric statistical techniques. Decis Sci. 2007;28(3):763-774.
[DOI] -
85. Raskin MS. The Delphi Study in Field Instruction Revisited: Expert Consensus on Issues and Research Priorities. J Soc Work Educ. 1994;30(14):75-89.
[DOI] -
86. Spinelli T. The Delphi decision-making process. J Psychol. 1983;113(1):73-80.
[DOI] -
87. Ahmadi F, Nasiriani K, Abazari P. Delphi technique, a tool in researches. Iran J Educ Med Sci. 2008;8(1):175-185. Available from: http://ijme.mui.ac.ir/article-1-790-fa.html
Copyright
© The Author(s) 2023. This is an Open Access article licensed under a Creative Commons Attribution 4.0 International License (https://creativecommons.org/licenses/by/4.0/), which permits unrestricted use, sharing, adaptation, distribution and reproduction in any medium or format, for any purpose, even commercially, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Commons license, and indicate if changes were made.
Share And Cite